Case Study

Our Strategy for Erecting and Dismantling a Tower Crane Safely

via Turner Construction

Our client, Turner Construction, needed assistance with the erection of the new covered seating area within Portland’s Providence Park. They also needed help with installing concrete structures at the park’s promenade level. We navigated a few challenges during this project, successfully erecting and dismantling large cranes within a limited space and achieving the project’s goals.

The Challenge

The biggest challenge we faced during this project pertained to space limitations. We had to work with tight site access, which meant strategically planning for safe crane erection and dismantling within a small area. Additionally, we had to navigate access challenges such as working with the local light rail system and bus lines and coordinating shared points of access with a local health club.

Stadium under construction with cranes | crane rental services | NessCampbell Crane + Rigging

The Solution

We approached this project by breaking each phase down into smaller sections. First, we determined a strategy for erecting and dismantling the tower crane safely. Next, we needed RT support to keep the concrete phase moving while the Tower Crane served other functions. We also needed to determine how to use large crawler cranes from the field level to set the truss sections and infill the stadium seats made of precast concrete. Finally, we had to coordinate the use of our GMK 5275 to hoist ironworkers in a fixed man basket to make the field connections in the air.

Why NessCampbell?

As a local crane and rigging company with 70 years of established partnerships throughout the Pacific Northwest, we emerged as the clear choice for this project. We were able to use our existing relationships to support our work and overcome challenges as they arose. Our company is a trusted leader in the construction industry, and our client looked to us to ensure that they met and exceeded their project goals.

Four cranes and trucks inside the Providence Park | crane services​​ | NessCampbell Crane + Rigging

The Outcome

We succeed in erecting the canopy and installing the new facilities safely and on time. One of our biggest wins was our ability to safely erect and dismantle the tower crane despite several limiting factors. Additionally, we were able to construct the canopy structure from the field level while maintaining a clear zone away from the underground stream beneath the stadium. We also safely and efficiently erected and dismantled large crawlers on the field level.

Equipment Used
  • Liebherr LTM 1500-8.1
  • GMK 5275
  • Linkbelt RTC80130 Series II
  • Linkbelt RTC8090 Series II
  • Two Manitowoc 16000 crawlers
  • Liebherr 542HC-L
  • Alimak 7100 Material Hoist
Logistics + Services Used
  • Transportation / Hauling
  • Equipment Operation
  • Signaling Team

Get Started

Get Started

Have questions about a project like this one? Start a conversation with our knowledgeable and dedicated team by contacting NessCampbell Crane + Rigging today.