Extensive Logistics Services to Support You with Various Project
Extensive Logistics Services to Assist You With All Phases of Your Project
Not only does NessCampbell employ highly qualified operators and possess an impressive fleet of cutting-edge equipment and machinery—we provide customized 3D Lift Drawings that have been engineered in-house and specifically designed to suit the parameters of your project.
Our team of industry experts will work with you at every phase of the project to ensure that it is completed safely and effectively.
Not only does NessCampbell employ highly qualified operators and possess an impressive fleet of cutting-edge equipment and machinery—we provide customized 3D Lift Drawings that have been engineered in-house and specifically designed to suit the parameters of your project.
Our team of industry experts will work with you at every phase of the project to ensure that it is completed safely and effectively.
COMMITMENT TO SAFETY
Our equipment is meticulously maintained, certified, inspected, and operated by the best, safest, most highly-certified operators in the business.
Specialized Haul Transformer Project Overview
NessCampbell Crane + Rigging was contracted to perform a turnkey transformer transport and installation for a 363,726 lb power transformer at a substation outside Jerome, Idaho. With a strict five-day deadline, our specialized haul and rigging teams completed field operations in just three days.
This complex project required expert coordination in hydraulic gantry lifting, specialized hauling, and precision jack-and-slide installation for critical utility infrastructure.
COMMITMENT TO SAFETY
Organization-wide safety through our comprehensive internal training program, NessCampbell University.
Specialized Haul Transformer Project Overview
NessCampbell Crane + Rigging was contracted to perform a turnkey transformer transport and installation for a 363,726 lb power transformer at a substation outside Jerome, Idaho. With a strict five-day deadline, our specialized haul and rigging teams completed field operations in just three days.
This complex project required expert coordination in hydraulic gantry lifting, specialized hauling, and precision jack-and-slide installation for critical utility infrastructure.