Case Study

The Seattle Tower was Built in Just One Day by NessCampbell

via Garco Construction

NessCambell was contacted by Garco Construction to erect a Tower Crane for work at the Washington State Convention Center in Downtown Seattle.

The Challenge

The City of Seattle’s permitting for tower crane erection is particularly challenging, providing a small assembly area for the tower crane erection.

A crane operating on a city building | Crane Rental Services | NessCampbell

The Solution

Pre-planning by our engineering team was key in ensuring the tower crane erection could take place in the small assembly area and within the strict regulations of Seattle’s permitting.

Why NessCampbell?

Pre-planning by our engineering team was key in ensuring the tower crane erection could take place in the small assembly area and within the strict regulations of Seattle’s permitting.

Man wearing safety glasses and orange shirt holding crane hook | Crane Services | NessCampbell

The Outcome

Erection was safely completed in just one day, allowing for the project to be completed on schedule.

Equipment Used
  • Grove GMK6300B 300-Ton
  • National Crane NBT 60-Ton
Logistics + Services Used
  • Engineering + Planning
  • Rigging
  • Equipment Operation
  • Signaling

Get Started

Get Started

We know Tower Crane Erection. Contact us today to get started on your project.